November 5, 2026
"We're gathering all that in and taking that to heart before we take any actions overturning dirt or raising the first dollar."
Brad Mills, co-chair of the We Are Evergreen committee, said that to Bellaire City Council on Sept. 14, 2026, as Community Impact reported. The quote explains why no ground has been broken at Evergreen Park, even after a design firm, two drawn concepts and more than 600 survey responses.
The plan that came out of that process is organized around money as much as design. The redesign will arrive in pieces. The playground is set to go first and the pool complex last. That order follows the gap between what has been raised so far and what the full project is expected to cost.
Evergreen Park covers about 2.1 acres where Newcastle and Evergreen meet, inside Loop 610. The city's planning solicitation dates it to 1955 and describes green space, playground equipment and a historic pool. In July 2025, Community Impact's coverage also listed picnic tables and open lawn alongside the neighborhood pool.
The goals for the redesign have stayed consistent: an all-abilities playground, a renovated pool complex and flexible green space, plus other upgrades. The city's request for qualifications asked for more than a drawing. It called for public engagement and a master plan covering phasing, entrances, access, parking, utilities, alternatives and cost estimates, with design and construction services to follow. Phasing was part of the assignment from the beginning.
The schedule slipped in a way that tells you a lot about the project. In December 2025, Council member Cindy Cohen-Taylor, who has led the effort on Council, said she expected a final conceptual design to go to a Council vote in January 2026. A capital campaign was to follow later in 2026. That vote didn't happen. The committee spent the year gathering more input.
| When | What happened |
|---|---|
| Late 2024 | City opens a resident survey on Evergreen Park |
| September 2024 | We Are Evergreen committee forms |
| April 2025 | Redevelopment adopted into the city's FY2026–28 strategic plan |
| April 30, 2025 | Deadline for design firms to respond to the city's RFQ |
| 2025 | TBG Partners hired for conceptual drawings |
| November 2025 | Two design concepts shown at an open house |
| Dec. 6, 2025 | Deadline for survey feedback on the two concepts |
| January 2026 | Council vote expected as of Dec. 2025; it did not take place |
| Sept. 14, 2026 | Committee reports community input complete |
| October 2026 | Council workshop on the conceptual plan anticipated as of Sept. 14 |
| Dec. 15, 2026 | Next Evergreen Park Committee meeting |
Across that year the committee collected more than 600 survey responses. It held focus groups, workshops and neighborhood meetings, talked with park users online and in person, and reviewed earlier redevelopment plans and past feedback, all in coordination with Bellaire's Parks, Recreation and Facilities Department. The official Sept. 14 Council minutes record the next step. The committee planned to present a conceptual plan at a Council workshop in October and then begin private fundraising.
The order matters. In December 2025, design approval was meant to come first and the fundraising campaign right after. By September 2026, the committee had added a stage for reaching agreement on the concept, and the money comes after that.
The funding figures explain the phasing. As of Dec. 1, 2025, the project had close to $700,000 in proceeds, according to Community Impact:
Cohen-Taylor put the total cost at roughly $6 million to $8 million and said the final number would depend on the design chosen. At that point, about a tenth of the expected cost was in hand.
The city's budget includes a placeholder for the rest. A question-and-answer document from the FY2026 budget process explains that the capital improvement schedule shows an $8 million appropriation planned for FY2028 under the Evergreen Park Improvements project. It also says the figure was set to reflect the committee's anticipated fundraising capacity, and that no specific recommendations had been made when it was written. So the $8 million is sized to what the committee expects to raise. It is not a lump sum of city money already set aside.
Donations to the committee go through a nonprofit partnership with the Houston-Galveston Area Council, according to We Are Evergreen's website.
With most of the money still to be raised, building everything at once was never realistic. The phasing presented in September, which the committee said could still change, looks like this:
The Council minutes describe the same order: improvements begin with the playground, and pool improvements come in the final phase.
This sequence puts the park's oldest signature feature last. The pool is the "historic" element in the city's own description of the park, and a question during the budget process asked whether an indoor or covered pool was being considered. It is also the part of the park that will wait longest for the money to arrive. A playground quadrant can be paid for and built while the larger campaign is still underway. A full pool renovation cannot.
Mills was direct about what the current step will and won't decide. "It's not locked down where we're definitely going to build and when we're going to build. It does not give us construction authorization. It does not give us funding approval," he told Council, as Community Impact reported. He described the request to Council as "conceptual alignment," meaning agreement on where the major building blocks go and confirmation that community concerns have been addressed.
Once Council agrees on the concept, the committee's to-do list becomes mostly about fundraising. According to the September presentation, We Are Evergreen plans to:
The fundraising packet ties back to the phasing. A donor can be asked to fund the playground, or a named feature within it, long before anyone is asked to fund a pool. The final professional design still depends on future Council approvals and available funding. Mills also said the committee intends to hold more community engagement events as it receives direction from Council.
Two December meetings on the city calendar are relevant to anyone following the project. The Evergreen Park Committee meets Dec. 15, 2026, at 4 p.m. in the BLIFE Activity Room at Bellaire City Hall. The Parks and Recreation Advisory Board meets the next evening, Dec. 16, at 6 p.m. at the CenterPoint Energy Community Center, 7001 Fifth Street. The committee works with Ryan Smith, Bellaire's Director of Parks, Recreation and Facilities, as its staff liaison.
When a park project near you is planned in phases, it helps to know which part comes first. If you'd like to talk through how Evergreen Park's timeline fits your own plans in Bellaire, Tahira Syed is glad to share what she's following on the project. Schedule a personalized market consultation.
Stay up to date on the latest real estate trends.
When it's time to move, you need someone who will advertise your home, show it to prospective buyers, negotiate the purchase contract, arrange to finance, oversee the inspections, handle all necessary paperwork and supervise the closing. Tahira can take care of everything you need, from start to close.